WINNER - Paving Industrial

Roseberry

Roseberry avenue water main and pavement reconstruction


Location: 9 Mile Road to Stephens - Warren
Concrete Contractor/Supplier: Florence Cement Company
Project Owner/Engineer: City of Warren

The Roseberry Avenue project required a full-depth pavement reconstruction along Roseberry from 9 Mile Road and Stephens in addition to water main relocation, minor storm sewer improvements, and edge drain installation.

The paving portion of the project could only commence once the underground work for the storm sewer and water main was completed. Then the road was constructed in halves, northbound and then southbound. Florence supplied and placed 8,088 square yards of 10-inch, non-reinforced concrete pavement and approximately 10,058 square feet of concrete sidewalk and drive approach.

This project was in an industrial area which required maintaining heavy truck traffic throughout the duration of construction. Proper gapping was created and used to maintain flow and complete the project.